Free change order form for subcontractors
Price extra work the right way: labor, material, equipment, lower-tier subs and markup, with the reference and schedule impact your GC needs to approve it. Print or save as PDF.
Free. No signup needed. Nothing you type leaves your browser.
CHANGE ORDER REQUEST
Change order request
Cost breakdown
| Type | Description | Qty | Unit | Unit cost | Amount | Remove |
|---|---|---|---|---|---|---|
| $1,520.00 | ||||||
| $880.00 | ||||||
| $1,180.00 | ||||||
| $420.00 | ||||||
| $150.00 | ||||||
| $380.00 |
| Labor | $2,400.00 |
| Material | $1,600.00 |
| Equipment | $150.00 |
| Other | $0.00 |
| Markup on own work | $622.50 |
| Subcontracts | $380.00 |
| Markup on subcontracts | $19.00 |
| Total change order amount | $5,171.50 |
Schedule impact: 2 calendar days. Pricing valid for 30 days. Work will proceed upon written approval of this change order.
Submitted by (subcontractor) / date
Approved by (general contractor) / date
How to get change orders approved faster
- 1Send it while the work is fresh. Price and submit within days, not at the end of the month.
- 2Reference the cause. Name the RFI, bulletin, drawing revision or directive. "Owner requested" isn't enough.
- 3Break out the cost. Separate labor hours and rates, material, equipment and lower-tier subs. Attach quotes.
- 4State the time. Include schedule impact in days, even if it's zero.
- 5Follow up and bill it. Track approval, then put the approved change on your next pay application.
More detail: change orders for subcontractors.
Frequently asked questions
What markup should a subcontractor put on a change order?
Use the markup allowed in your subcontract. Many contracts set separate limits for markup on your own work and on lower-tier subcontractors. If the contract is silent, price a markup that covers your overhead and profit, and state it clearly.
Should I include schedule impact on a change order?
Yes. If the change adds time, state the number of days. On many contracts, signing a change order with zero days can waive your right to a time extension later.
What backup should I attach?
The RFI, bulletin, drawing revision or written directive that caused the change, plus supplier quotes, lower-tier sub quotes, and labor hours or field tickets for time-and-material work.
Does this form save my data?
No. Everything stays in your browser. Print or save as PDF before closing. Sub-Office saves every change order, tracks approval and carries approved changes into your pay applications.
Spend less time on paperwork and more time building.
Try Sub-Office free for 30 days. No credit card required, cancel anytime. Then $25 per user per month.